During the test run of the dolomite powder machine under load, according to the proportion of the dolomite powder machine, a certain amount of steel balls are added to the barrel of the dolomite powder machine, and the steel balls are added in batches. During the operation process, the bearing temperature, current, and vibration intensity are measured.
After the dolomite powder machine is installed, start running with load, add 70% of the specified load to the grinding material, and continue to run for more than 10 hours. During the process, the threaded joints of the dolomite powder machine lining should be tightened and the threaded connections should be checked frequently to prevent loosening.